Kehl St Fall Build 2022
Habitat for Humanity: Kitchener Waterloo Ontario Canada
Thursday, November 30, 2017
door transfers
stair walls and cold cellar door
painting through the mist
screwing down the floors
insulating the garage door
Wednesday, November 29, 2017
paint booth
getting the garage ready
stair case walls
getting the floors ready
Tuesday, November 28, 2017
furnace installation
screwing down the floors
Tuesday, November 21, 2017
yea! all the siding will be done today
Monday, November 20, 2017
building some scaffolding
blue board in the basement
a day of siding
marking for screwing down the floors
one porch done
alcove done
near the end of the day
Thursday, November 16, 2017
concrete for the basement
siding
porch pour
a bit of drywall cleanup
getting the basement ready
part of the back done
Wednesday, November 15, 2017
cleaning out the next garage
drywalling
siding
ready for the next pour
Tuesday, November 14, 2017
concrete for floor and garage
start of siding on back
garage pour
finishing the basement floor
finishing garage floor
repositioning window
window back in