Kehl St Fall Build 2022
Habitat for Humanity: Kitchener Waterloo Ontario Canada
Tuesday, December 14, 2021
H Block numbers up
the decking on three units done
Monday, December 13, 2021
insulating the floors
Gravel for drainage
sump pits
getting ready for the insulation on the floor
cleaning up before the painting
Monday, November 29, 2021
Moving along
Getting Dimple fasteners ready
Monday, November 8, 2021
SIPs going up
Thursday, November 4, 2021
hoisting the beams in place
Wednesday, November 3, 2021
continuation of the SIP forms
Friday, October 29, 2021
insulating the trailer
installing the SIP panels
Thursday, October 28, 2021
getting the sip panels ready
Wednesday, October 27, 2021
The foundation walls have started
Tuesday, October 26, 2021
back to painting doors
hanging doors
cutting railings
Wednesday, October 20, 2021
one of our volunteers pride and joy